- Locate rotten post to be replaced. Detach siding and remove existing
skirt board.
- Dig down next to face and sides of rotten post with auger.
- Support truss with brace and hydraulic jack.
- Cut rotten post off at ground level. No measuring necessary at this point.
- Remove rotten portion of post.
- Clean out post hole to provide a level, compacted base for the pre-cast
concrete pad. Sakrete or ready mix concrete can also be used for post base.
- Install pad and measure the Perma-Column for exact clearance needed.
*Note: Perma-Column length may vary.
- Mark existing post and cut to desired clearance for Perma-Column
installation.
- Install and position Perma-Column.
- Install 1/4" x 3" wood lags. Drill and install (2) 1/2" bolts.
- Reattach siding and skirt board.
*Building renovation is hazardous and should only be performed by a
construction professional.